Total night closures of I-5 in Fife completed ahead of schedule
FIFE – Completing work ahead of schedule, construction crews successfully set the remaining seven out of 15 girders for a new bridge over Interstate 5 in Fife during the weekend of Oct. 11-13, 2024. As a result, the fourth weekend of overnight closures planned for Oct. 18-20, 2024 is canceled.
The next step of building the temporary framework around the new girders will require closing four out of five lanes in both directions of I-5 nightly Monday, Oct. 14 through the morning of Friday, Oct. 18. After the framework is in place, crews can begin placing rebar and concrete for the bridge deck. The bridge is a key element of the State Route 167 Completion Project.